Construction Progress: September Update

The construction team from Plant are making swift progress on construction for the redevelopment of Public Market Emeryville. All shops and businesses, including the Food Hall, offices, Urban Outfitters, Guitar Center, Hot Italian, Paradita Eatery, and Peet’s are open for business.

We’re publishing regular updates to keep everyone informed about the latest news on construction. Sign up here to receive our monthly newsletter >

As underground utilities are being installed, the Plant team is fencing off areas of parking in limited phases. During this phased construction, there will always be ample parking for customers and access for pedestrians. We’ve installed plenty of signage to direct you to ensure your visit to Public Market is easy.

We recently caught up with Travis from Plant to learn about the latest construction milestones and what’s next in the pipeline. Below are a few of the highlights:

  • The new domestic water line will be completed and placed into service this month.
  • We will be turning over North Market Drive and a portion of 63rd Street to the City of Emeryville mid-September.
  • We plan to open the new parking garage above New Seasons in late September.
  • We are also going to start installing the brick pavers that will make up the plaza on 62nd Street.